photo Nurito - Beritajakarta.id

Ciliwung River Normalization in Bukit Duri Accelerated

The normalization of Ciliwung River in Bukit Duri, Tebet, South Jakarta is accelerated. At this moment, pole installation for sheet pile at the river has reached 1,300 meters.

Total execution is targeted in December

It is targeted that the installation along 2,000 meters will complete December 2016.

“Total execution is targeted in December,” said Teuku Iskandar, BBWSCC Head, Monday (10/31).

Illegal Buildings at Krukut Riverbank Controlled

After installing the sheet pile, his side will install parapet wall along 2,000 meters. According to him, the normalization project has no problem so far.

“We’ll also install sheet pile along 700 meters at Gang Arus Cawang, Kramat Jati. Heavy equipments have been prepared at the site,” he closed.

Linked News
Popular News indeks
  1. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye357 personTiyo Surya Sakti
  2. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye328 personAldi Geri Lumban Tobing
  3. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye318 personAldi Geri Lumban Tobing
  4. Rivers with Severe Pollution in Jakarta Decrease

    access_time18-07-2025 remove_red_eye235 personAldi Geri Lumban Tobing
  5. Council Encourages the Increase of RPTRAs for Child Growth and Development

    access_time18-07-2025 remove_red_eye227 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik